Current Construction Updates
School | Start | Open | Percent Complete |
---|---|---|---|
Spring 2022 | Fall 2024 | 100% | |
Spring 2023 | Fall 2025 | 80% | |
Spring 2024 | Fall 2026 | 50% | |
Spring 2024 | Fall 2025 | 43% |
2018 Bond Updates
Project | Status | Actual or Estimated Start Date | Actual or Estimated End Date | Construction Bid and Actual or | Final Cost |
---|---|---|---|---|---|
Valley View Middle School | Completed | February 2019 | August 2020 | $ 37,972,701 | $ 37,972,701 |
Spring Canyon Middle School | Completed | February 2020 | August 2021 | $ 39,085,861 | $ 39,085,861 |
Maple Grove Middle School | Completed | February 2020 | August 2021 | $ 39,188,946 | $ 39,188,946 |
Spanish Fork High School | In Progress | June 2020 | August 2024 | $ 127,431,753 | TBD |
Payson High School | In Progress | June 2022 | August 2025 | $ 143,024,495 | TBD |
Springville High School | In Progress | December 2022 | August 2026 | $ 177,683,183 | TBD |